Projects | All projects
Sort by:year square footage
«
1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12 - 13 - 14 - 15 - 16 - 17 - 18 - 19
»
BMW Sainte-Julie 2005  |  15,900 sf
Contract delivery :
Design Build Mechanical, Fixed Price
BMW dealership, including full glass curtain wall façade, service and wash bay facilities, and administrative offices
Au Village du Musée 2005  |  60,455 sf
Contract delivery :
Construction Management
A 5-storey condominium development consisting of 6,000 sf of below ground parking, upgrade lobby and 47 finished luxury condo units. Reliance was responsible for completion and fit up of all 47 units according to the individual owner's requirements, including renovation to an existing building (circa 1890) configured for 5 ultra-luxurious "historic" condo units.
Moores Clothing 2004  |  84,500 sf
Contract delivery :
New 84,500 sf distribution center including 6,000 sf of offices and 120,000 sf of “veit” conveyor/racking system on 3 floors within the warehouse.
Labrador 2004  |  74,000 sf
Contract delivery :
Design Build Mechanical, Fixed Price
New 74,000 sf head office for the natural spring water company serving as corporate offices and a shipping/distribution center complete with drive-through loading docks and 32’-0” high steel structure for storage
Karmin Industries 2004  |  90,000 sf
Contract delivery :
Design Build, Fixed Price
Office and warehousing facility.
JAM Industries 2004  |  85,000 sf
Contract delivery :
Extension to existing distribution center, including offices, music labs and humidification controlled storage areas.
Indalex 1995, 2000, 2004  |  295,000 sf
Contract delivery :
Design Build Mechanical, Fixed Price
Aluminum extrusion facility housing eastern Canada head offices. Originally constructed in 1995 as a 200,000 sf plant, further enlarged by 50,000 sf in 2000 and an additional 45,000 sf in 2004. The site selected for this building contained a 40'-0" wide river running through it which was excavated and backfilled during the winter months without any impact to the project schedule. The last extension in May 2004 included bases for a $2,000,000 press and underground service trenches.
Fly America 2002, 2003, 2004  |  3 stores 60,000-75,000 sf
Contract delivery :
Design Build Mechanical, Fixed Price
Reliance completed the first three Fly Stores (Laval, St. Laurent and St. Hubert, Quebec) in North America building on designs and concepts brought to Canada by the French furniture chain to Montreal in 2002. Each store is between 60,000 and 75,000 sf and each was completed in less than 4 months. Our role in all three of these initial North American stores included the constant coordination and assistance to the building owner and design professionals to adapt the European design to the North American market (choice of materials, design techniques and building envelope solutions).
Dollarama 2 2004  |  260,000 sq.ft.
Contract delivery :
Construction Management, Design Build Mechanical
Construction of two new warehouses totalling 260,000 sf utilized as a distribution center and built on fast track basis in just 3 and a half months. The warehouse has a 28' 0" clear hight and is equipped with ESFR sprinkler systems. The building is a combination of precast architectural concrete and metal siding façades.
The Brick Montreal Distribution Center 2003  |  332,000 sf
Contract delivery :
Construction Management, Design Build
New distribution center of 332,000 square feet for The Brick retail store chain was built to satisfy its current needs in eastern Canada. This building serves as phase I of its eastern Canada expansion plan, allowing for an additional expansion of warehouse space of 195,000 square feet. The warehouse space is fully air-conditioned, with 40'-0"clear racking height, and superflat floor slabs of Fmin 65 for an electronic wire guide racking storage system. The 10,000 square foot regional office and customer service pick-up area form the balance of the building.
«
1 - 2 - 3 - 4 - 5 - 6 - 7 - 8 - 9 - 10 - 11 - 12 - 13 - 14 - 15 - 16 - 17 - 18 - 19
»