North Cargo Village, 2009, 330,000 sq.ft.
Location :
Dorval, Quebec
Contract Delivery :
Construction Management
This 8 month long, $35M turn-key project was
constructed for the developer Aeroterm to house air cargo tenants such as Air
Canada, Mercury, and Schenker. The project consists of 2 buildings, sitting on
approximately 1,000,000 sf of land, with exterior envelopes consisting of
precast concrete, curtain wall and prefabricated insulated metal panels. The
careful selection of materials for the exterior wall was primarily based on the
period during the year in which the work was to be executed. The sitework
included large parking areas, loading docks and roads circulating on the air
side to transport cargo to and from aircraft. Over 60,000 sf of administrative
areas were fit up for tenants to manage the cargo, including special provisions
for conveyors, scales, specialized equipment and cold rooms.
|